Revision as of 22:13, 19 July 2012 editPrioryman (talk | contribs)Autopatrolled, Extended confirmed users, IP block exemptions, Pending changes reviewers27,962 edits →Opening: - add section← Previous edit | Latest revision as of 23:29, 3 December 2024 edit undoEntranced98 (talk | contribs)Extended confirmed users, Pending changes reviewers, Rollbackers173,625 edits Importing Wikidata short description: "Road tunnel in Dorset, UK"Tag: Shortdesc helper | ||
(68 intermediate revisions by 27 users not shown) | |||
Line 1: | Line 1: | ||
{{Short description|Road tunnel in Dorset, UK}} | |||
⚫ | |||
{{Use dmy dates|date=February 2014}} | |||
The '''Beaminster Tunnel''' or '''Horn Hill Tunnel''' is a {{convert|345|ft|m|adj=on}} long ] between ] and ] in ], in the United Kingdom. The tunnel was constructed between 1830–1832; it is notable for being one of the first road tunnels built in Britain and the only pre-railway road tunnel in the country still in use. | |||
{{Use British English|date=February 2014}} | |||
{{Infobox tunnel | |||
|name = Beaminster Tunnel | |||
⚫ | |image = North portal of Horn Hill tunnel - geograph.org.uk - 709458.jpg | ||
|image_size = | |||
|caption = The north portal of Beaminster Tunnel, before the collapse of 7 July 2012 | |||
|location = ], ] | |||
⚫ | |coordinates = {{coord|50.826|-2.757|dim:150|display=inline,title}} | ||
|route = ], ] to ] road | |||
|status = | |||
|start = | |||
|end = | |||
|startwork = 1830 | |||
|opened = {{Start date|1832|06|29|df=y}} | |||
|close = | |||
|owner = | |||
|operator = | |||
|traffic = | |||
|character = | |||
|vpd = | |||
|construction = Brick, lined with ] | |||
|length = {{convert|345|ft|m|adj=on}} | |||
|lanes = | |||
|speed = | |||
|hielevation = | |||
|lowelevation = | |||
|height = | |||
|width = | |||
|grade = | |||
}} | |||
'''Beaminster Tunnel''' or '''Horn Hill Tunnel''' is a {{convert|345|ft|m|adj=mid|-long}} ] on the ] between ] and ] in ], England. The tunnel was constructed between 1830 and 1832; it was one of the first road tunnels built in Britain, and is the only pre-railway road tunnel in the country still in use.{{citation needed|date=July 2017}} It was built to take a ] underneath a steep hill to the north of Beaminster and make it easier for horse-drawn traffic to travel from the coast to the hinterland of Dorset. It underwent significant repairs in 1968 and again in 2009, but in 2012 a torrential rainstorm caused a landslide that resulted in the partial collapse of the tunnel's north entrance and the deaths of two people. | |||
==Construction== | ==Construction== | ||
The tunnel is constructed from brick with walls {{convert|3|ft|6|in|m}} thick. It runs for {{convert|345|ft|m}} under Horn Hill, a {{convert|650|ft|m}} |
The tunnel is constructed from brick with walls {{convert|3|ft|6|in|m|abbr=on}} thick, faced with ].<ref name="Bridges">{{cite book|title=British Bridges: An Illustrated Technical and Historical Record|publisher=Organising Committee of the Public Works, Roads and Transport Congress|location=London|year=1933|page=79}}</ref> It runs for {{convert|345|ft|m}} under Horn Hill, a {{convert|650|ft|m|adj=mid|-high}} promontory to the north of Beaminster. The hill presented a major barrier to travellers passing from the newly enlarged harbour at ] on the Dorset coast to the hinterland; according to a contemporary writer, the hill was "a great impediment to the communication between the lower portion of Dorsetshire and a considerable district of Somerset, particularly with regard to ] harbour."<ref>{{cite book|title=Domestic occurrences|work=The Gentleman's Magazine|date=July 1832|page=74}}</ref> The main road passed over the hill, climbing almost 500 feet in a mile-and-a-half (150 metres in two kilometres).<ref name="Headley">{{cite news|url=http://www.dorsetlife.co.uk/2010/11/%E2%80%98a-tunnel-wide%E2%80%99/|title='A tunnel wide'|last=Headley|first=Andrew|work=Dorset Life|date=November 2010|accessdate=17 July 2012}}</ref> The steep gradient of 1-in-6 (17%) made passage difficult for horse-drawn transport.<ref name="Otter">{{cite book|title=Civil Engineering Heritage: Southern England|last=Otter|first=R.A.|publisher=Thomas Telford|year=1994|isbn=9780727719713}}</ref> In the late 1820s, a Beaminster solicitor named Giles Russell proposed that the owners of the toll road over the hill, the Bridport 2nd District Turnpike Trust, should seek to build a tunnel under it to shorten and flatten the road. Russell played a key role in getting the project underway and managed to raise the £13,000 required through loans and contributions from many of Beaminster's artisans and traders.<ref name="Headley" /> | ||
In March 1830 Parliament |
In March 1830 Parliament passed the ''Bridport Turnpike Trust (Second District) Act, 1830''<ref name="Bridges" /> authorising construction of the tunnel, which began the following month. The engineer ], a colleague of ] who had worked on the pioneering ] in ], was in charge of the project, which took just over two years to complete. Only one fatality was sustained, a worker named William Aplin who died only three days before the tunnel opened when he was struck by a landslide outside one of the tunnel entrances. He was memorialised with a stone marked with a white cross which can still be seen ''in situ''.<ref name="Headley" /> The tunnel reduced the road's gradient from 1-in-6 (17%) to 1-in-10 (10%) and shortened it by a mile (1.6 km), as well as lowering its maximum elevation by {{convert|50|ft|m}}.<ref name="Otter" /> At the time of its opening, only a handful of road tunnels had been built in Britain;<ref name="Headley" /> it pre-dates the construction of the first railway tunnels, and it is now the only pre-railway road tunnel in the country still in use.<ref>{{cite web|url=http://www.beaminster-tc.gov.uk/History%20of%20Beaminster.html|title=Beaminster: A Little History|publisher=Beaminster Town Council|accessdate=19 July 2012|archive-date=20 December 2012|archive-url=https://web.archive.org/web/20121220031325/http://www.beaminster-tc.gov.uk/History%20of%20Beaminster.html|url-status=dead}}</ref> | ||
] | |||
===Opening=== | ===Opening=== | ||
The tunnel was formally opened on 29 June 1832 with enthusiastic celebrations including |
The tunnel was formally opened on 29 June 1832 with enthusiastic celebrations including a ] fired from the top of the hill, a firework display and the launching of a ]. A procession of dignitaries, local people and the tunnel workers paraded through the tunnel accompanied by three flag-bearers, two bands, the project's patron in a four-horse open carriage and the Commissioners of the Trust and various officials in a mail wagon.<ref name="Bridges" /> A celebratory dinner was held afterwards in the White Hart inn in Beaminster, where Giles Russell was the guest of honour.<ref name="Headley" /> A song was especially written for the occasion, including the lyrics: | ||
<blockquote> | <blockquote> | ||
Line 24: | Line 58: | ||
</blockquote> | </blockquote> | ||
Commemorations of the opening of the tunnel became an annual tradition in Beaminster with "Tunnel Fairs" being held every Good Friday on Horn Hill until about the 1880s. In 1881, the tunnel became free to use when the tollgates were removed and the toll house at the north end was converted into a dwelling for the tunnel's lamplighter. The house was later demolished to allow the road to be widened.<ref name="Headley" /> | Commemorations of the opening of the tunnel became an annual tradition in Beaminster with "Tunnel Fairs" being held every Good Friday on Horn Hill until about the 1880s. In 1881, the tunnel became free to use when the tollgates were removed and the toll house at the north end was converted into a dwelling for the tunnel's lamplighter. The house was later demolished to allow the road to be widened.<ref name="Headley" /> The two entrance portals are ] as being of Special Architectural or Historic Interest.<ref name="Otter" /> | ||
==Renovation and repairs== | ==Renovation and repairs== | ||
By the 1960s, 130 years of exposure to the elements had resulted in the tunnel's brick walls crumbling from the effects of frost. To prevent falls of frost-damaged bricks, a cement mix known as ] was sprayed onto the walls to stabilise them. However, this in turn became detached from the brickwork and in |
By the 1960s, 130 years of exposure to the elements had resulted in the tunnel's brick walls crumbling from the effects of frost. To prevent falls of frost-damaged bricks, a cement mix known as ] was sprayed onto the walls to stabilise them. However, this in turn became detached from the brickwork, and in October–November 2009 the tunnel was closed to carry out repairs. The gunite layer was re-fixed to the brickwork using bolts and painted, and the drainage systems and portal arches were also renovated. The tunnel's lighting system was replaced at the same time, and the carriageway was also resurfaced.<ref>{{cite news|url=http://www.viewfrompublishing.co.uk/news_view/2346/14/1/tunnel-to-undergo-major-refurbishment|title=Tunnel to undergo major refurbishment|last=Hookings|first=Margaret|date=22 October 2009|accessdate=19 July 2012|work=View from Beaminster|archive-url=https://web.archive.org/web/20160303220255/http://www.viewfrompublishing.co.uk/news_view/2346/14/1/tunnel-to-undergo-major-refurbishment|archive-date=3 March 2016|url-status=dead|df=dmy-all}}</ref><ref>{{cite news|url=http://www.thisisdorset.co.uk/Historic-tunnel-opens-extensive-works/story-11786195-detail/story.html |archive-url=https://archive.today/20130505130904/http://www.thisisdorset.co.uk/Historic-tunnel-opens-extensive-works/story-11786195-detail/story.html |url-status=dead |archive-date=5 May 2013 |title=Historic tunnel re-opens after extensive works |date=1 December 2009 |accessdate=19 July 2012 |work=This is Dorset }}</ref> | ||
==July 2012 partial collapse== | |||
==Incidents== | |||
At 22:10 on 7 July 2012, |
At around 22:10 on 7 July 2012, Rosemary Snell and Michael Rolfe,<ref name="BBC-2012-07-23">{{cite web|url=https://www.bbc.co.uk/news/uk-england-somerset-18962892|title=BBC News – Dorset landslip: Burglars target home of Rosemary Snell|date=2012-07-23|work=]|accessdate=28 July 2012}}</ref> from Somerset,<ref name="BBC-2012-07-23" /> were driving through the tunnel and were caught in a partial collapse of the north entrance, caused by torrential rain. Several hundred tons of mud, earth, stones and vegetation fell onto the road and crushed their car, killing them. The flattened vehicle was entirely buried and was not found until 10 days later after the two were reported missing, prompting police to carry out a search of the debris.<ref>{{cite news|url=https://www.theguardian.com/uk/2012/jul/17/two-feared-dead-dorset-landslide|title=Two feared dead in Dorset landslide|last=Morris|first=Stephen|work=The Guardian|date=17 July 2012|accessdate=19 July 2012|quote=It's very sad to think that someone could have buried in there for 10 days and we didn't know it.}}</ref> Their deaths were later ruled by a ] to have been accidental.<ref name="Council tree" /> | ||
The local ] force was criticised for failing to find the bodies sooner and the case was voluntarily referred to the ] (IPCC) to be reviewed,<ref>{{cite news|url=https://www.theguardian.com/uk/2012/jul/18/beaminster-tunnel-deaths-police-ipcc|title=Beaminster tunnel landslip deaths: police force refers itself to IPCC|first=Steven|last=Morris|work=The Guardian|date=19 July 2012|accessdate=19 July 2012}}</ref> but the IPCC subsequently declined to open an investigation.<ref>{{cite news|url=https://www.independent.co.uk/news/uk/home-news/no-ipcc-investigation-to-take-place-into-dorset-landslide-deaths-7966112.html|title=No IPCC investigation to take place into Dorset landslide deaths|last=Hallett|first=Emma|work=The Independent|date=23 July 2012|accessdate=20 November 2016}}</ref> | |||
⚫ | ==References== | ||
⚫ | {{reflist}} | ||
Although there were claims that tree-felling by ] workers could have destabilised the slope above the tunnel portal, expert opinion suggested that the landslide had been triggered by a poorly-maintained drainage ditch above the tunnel breaching during the rainstorm, causing a sudden flood of water into an already saturated area.<ref name="Council tree">{{cite news|url=https://www.telegraph.co.uk/news/uknews/road-and-rail-transport/10660626/Council-tree-felling-may-have-caused-landslide-which-killed-couple-inquest-told.html|title=Council tree felling may have caused landslide which killed couple, inquest told|last=Prynne|first=Miranda|work=The Daily Telegraph|date=25 February 2014|accessdate=20 November 2016}}</ref> | |||
⚫ | {{coord|50.826|-2.757|dim:150|display=title}} | ||
In the aftermath of the collapse, five options were put forward to remedy the tunnel, including stabilising the slope, permanently extending the tunnel, removing some of the soil from the hillside above the tunnel, removing the tunnel and building a cutting or bypassing the tunnel.<ref>{{cite web|url=http://www.dorsetforyou.com/beaminstertunnel |title=Beaminster Tunnel |publisher=Dorset County Council |date=1 November 2012 |accessdate=1 November 2012 |url-status=dead |archiveurl=https://web.archive.org/web/20121023152758/http://www.dorsetforyou.com/beaminstertunnel |archivedate=23 October 2012 |df=dmy }}</ref> A public consultation held in October 2012 found public support for the option of building a concrete hood at the entrance to the tunnel. It was estimated that this would cost about £1.75 million and would take about six months to complete.<ref>{{cite news|url=https://www.bbc.co.uk/news/uk-england-dorset-19998479|title=Dorset landslip deaths: Beaminster Tunnel hood supported|publisher=BBC News|date=19 October 2012|accessdate=1 November 2012|quote=the concrete hood option would take about six months to complete and could cost up to £1.75m.}}</ref> The Department of Transport refused at the time to provide extra funding to meet the cost.<ref>{{cite news|url=https://www.bbc.co.uk/news/uk-england-dorset-20150655|title=Beaminster Tunnel: No Department for Transport funding|publisher=BBC News|date=31 October 2012|accessdate=1 November 2012}}</ref> | |||
The tunnel reopened on 29 July 2013 following £2 million of work.<ref>{{cite news|url=http://www.itv.com/news/west/story/2013-07-29/beaminster-tunnel-reopens-to-traffic/|title=Beaminster Tunnel reopens|date=29 July 2013|accessdate=2 February 2014|first=Duncan|last=Sleightholme|work=ITV News}}</ref> By February 2014, it was reported that Dorset County Council had spent around £2.5 million on remedial works around the tunnel.<ref name="Council tree" /> | |||
⚫ | ==References== | ||
⚫ | {{reflist|2}} | ||
] | ] | ||
] | ] | ||
⚫ | ] | ||
] | ] | ||
⚫ | ] | ||
] | |||
] | |||
] |
Latest revision as of 23:29, 3 December 2024
Road tunnel in Dorset, UK
The north portal of Beaminster Tunnel, before the collapse of 7 July 2012 | |
Overview | |
---|---|
Location | Dorset, England |
Coordinates | 50°49′34″N 2°45′25″W / 50.826°N 2.757°W / 50.826; -2.757 |
Route | A3066, Beaminster to Mosterton road |
Operation | |
Work begun | 1830 |
Constructed | Brick, lined with gunite |
Opened | 29 June 1832 (1832-06-29) |
Technical | |
Length | 345-foot (105 m) |
Beaminster Tunnel or Horn Hill Tunnel is a 345-foot-long (105 m) road tunnel on the A3066 road between Beaminster and Mosterton in Dorset, England. The tunnel was constructed between 1830 and 1832; it was one of the first road tunnels built in Britain, and is the only pre-railway road tunnel in the country still in use. It was built to take a toll road underneath a steep hill to the north of Beaminster and make it easier for horse-drawn traffic to travel from the coast to the hinterland of Dorset. It underwent significant repairs in 1968 and again in 2009, but in 2012 a torrential rainstorm caused a landslide that resulted in the partial collapse of the tunnel's north entrance and the deaths of two people.
Construction
The tunnel is constructed from brick with walls 3 ft 6 in (1.07 m) thick, faced with Hamstone. It runs for 345 feet (105 m) under Horn Hill, a 650-foot-high (200 m) promontory to the north of Beaminster. The hill presented a major barrier to travellers passing from the newly enlarged harbour at West Bay on the Dorset coast to the hinterland; according to a contemporary writer, the hill was "a great impediment to the communication between the lower portion of Dorsetshire and a considerable district of Somerset, particularly with regard to Bridport harbour." The main road passed over the hill, climbing almost 500 feet in a mile-and-a-half (150 metres in two kilometres). The steep gradient of 1-in-6 (17%) made passage difficult for horse-drawn transport. In the late 1820s, a Beaminster solicitor named Giles Russell proposed that the owners of the toll road over the hill, the Bridport 2nd District Turnpike Trust, should seek to build a tunnel under it to shorten and flatten the road. Russell played a key role in getting the project underway and managed to raise the £13,000 required through loans and contributions from many of Beaminster's artisans and traders.
In March 1830 Parliament passed the Bridport Turnpike Trust (Second District) Act, 1830 authorising construction of the tunnel, which began the following month. The engineer Michael Lane, a colleague of Marc Brunel who had worked on the pioneering Thames Tunnel in London, was in charge of the project, which took just over two years to complete. Only one fatality was sustained, a worker named William Aplin who died only three days before the tunnel opened when he was struck by a landslide outside one of the tunnel entrances. He was memorialised with a stone marked with a white cross which can still be seen in situ. The tunnel reduced the road's gradient from 1-in-6 (17%) to 1-in-10 (10%) and shortened it by a mile (1.6 km), as well as lowering its maximum elevation by 50 feet (15 m). At the time of its opening, only a handful of road tunnels had been built in Britain; it pre-dates the construction of the first railway tunnels, and it is now the only pre-railway road tunnel in the country still in use.
Opening
The tunnel was formally opened on 29 June 1832 with enthusiastic celebrations including a 21-gun salute fired from the top of the hill, a firework display and the launching of a hot air balloon. A procession of dignitaries, local people and the tunnel workers paraded through the tunnel accompanied by three flag-bearers, two bands, the project's patron in a four-horse open carriage and the Commissioners of the Trust and various officials in a mail wagon. A celebratory dinner was held afterwards in the White Hart inn in Beaminster, where Giles Russell was the guest of honour. A song was especially written for the occasion, including the lyrics:
The yielding soil, through able hands,
A tunnel wide displays;
And Lane’s efficient aid demands
Our warm, admiring praise
In swelling streams may cheering wealth
To Beaminster descend:
And ever joy-inspiring health
Her social sons attend.
Commemorations of the opening of the tunnel became an annual tradition in Beaminster with "Tunnel Fairs" being held every Good Friday on Horn Hill until about the 1880s. In 1881, the tunnel became free to use when the tollgates were removed and the toll house at the north end was converted into a dwelling for the tunnel's lamplighter. The house was later demolished to allow the road to be widened. The two entrance portals are Grade II listed as being of Special Architectural or Historic Interest.
Renovation and repairs
By the 1960s, 130 years of exposure to the elements had resulted in the tunnel's brick walls crumbling from the effects of frost. To prevent falls of frost-damaged bricks, a cement mix known as gunite was sprayed onto the walls to stabilise them. However, this in turn became detached from the brickwork, and in October–November 2009 the tunnel was closed to carry out repairs. The gunite layer was re-fixed to the brickwork using bolts and painted, and the drainage systems and portal arches were also renovated. The tunnel's lighting system was replaced at the same time, and the carriageway was also resurfaced.
July 2012 partial collapse
At around 22:10 on 7 July 2012, Rosemary Snell and Michael Rolfe, from Somerset, were driving through the tunnel and were caught in a partial collapse of the north entrance, caused by torrential rain. Several hundred tons of mud, earth, stones and vegetation fell onto the road and crushed their car, killing them. The flattened vehicle was entirely buried and was not found until 10 days later after the two were reported missing, prompting police to carry out a search of the debris. Their deaths were later ruled by a coroner to have been accidental.
The local Dorset Police force was criticised for failing to find the bodies sooner and the case was voluntarily referred to the Independent Police Complaints Commission (IPCC) to be reviewed, but the IPCC subsequently declined to open an investigation.
Although there were claims that tree-felling by Dorset County Council workers could have destabilised the slope above the tunnel portal, expert opinion suggested that the landslide had been triggered by a poorly-maintained drainage ditch above the tunnel breaching during the rainstorm, causing a sudden flood of water into an already saturated area.
In the aftermath of the collapse, five options were put forward to remedy the tunnel, including stabilising the slope, permanently extending the tunnel, removing some of the soil from the hillside above the tunnel, removing the tunnel and building a cutting or bypassing the tunnel. A public consultation held in October 2012 found public support for the option of building a concrete hood at the entrance to the tunnel. It was estimated that this would cost about £1.75 million and would take about six months to complete. The Department of Transport refused at the time to provide extra funding to meet the cost.
The tunnel reopened on 29 July 2013 following £2 million of work. By February 2014, it was reported that Dorset County Council had spent around £2.5 million on remedial works around the tunnel.
References
- ^ British Bridges: An Illustrated Technical and Historical Record. London: Organising Committee of the Public Works, Roads and Transport Congress. 1933. p. 79.
- Domestic occurrences. July 1832. p. 74.
{{cite book}}
:|work=
ignored (help) - ^ Headley, Andrew (November 2010). "'A tunnel wide'". Dorset Life. Retrieved 17 July 2012.
- ^ Otter, R.A. (1994). Civil Engineering Heritage: Southern England. Thomas Telford. ISBN 9780727719713.
- "Beaminster: A Little History". Beaminster Town Council. Archived from the original on 20 December 2012. Retrieved 19 July 2012.
- Hookings, Margaret (22 October 2009). "Tunnel to undergo major refurbishment". View from Beaminster. Archived from the original on 3 March 2016. Retrieved 19 July 2012.
- "Historic tunnel re-opens after extensive works". This is Dorset. 1 December 2009. Archived from the original on 5 May 2013. Retrieved 19 July 2012.
- ^ "BBC News – Dorset landslip: Burglars target home of Rosemary Snell". BBC Online. 23 July 2012. Retrieved 28 July 2012.
- Morris, Stephen (17 July 2012). "Two feared dead in Dorset landslide". The Guardian. Retrieved 19 July 2012.
It's very sad to think that someone could have buried in there for 10 days and we didn't know it.
- ^ Prynne, Miranda (25 February 2014). "Council tree felling may have caused landslide which killed couple, inquest told". The Daily Telegraph. Retrieved 20 November 2016.
- Morris, Steven (19 July 2012). "Beaminster tunnel landslip deaths: police force refers itself to IPCC". The Guardian. Retrieved 19 July 2012.
- Hallett, Emma (23 July 2012). "No IPCC investigation to take place into Dorset landslide deaths". The Independent. Retrieved 20 November 2016.
- "Beaminster Tunnel". Dorset County Council. 1 November 2012. Archived from the original on 23 October 2012. Retrieved 1 November 2012.
- "Dorset landslip deaths: Beaminster Tunnel hood supported". BBC News. 19 October 2012. Retrieved 1 November 2012.
the concrete hood option would take about six months to complete and could cost up to £1.75m.
- "Beaminster Tunnel: No Department for Transport funding". BBC News. 31 October 2012. Retrieved 1 November 2012.
- Sleightholme, Duncan (29 July 2013). "Beaminster Tunnel reopens". ITV News. Retrieved 2 February 2014.