Misplaced Pages

Draft:Sankhuwa Khola Hydropower project: Difference between revisions

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
Browse history interactively← Previous editContent deleted Content addedVisualWikitext
Revision as of 03:57, 12 July 2024 editFrost (talk | contribs)Extended confirmed users, Page movers, New page reviewers, Pending changes reviewers, Rollbackers54,748 editsm Ae245 moved page Sankhuwa Khola Hydropower project to Draft:Sankhuwa Khola Hydropower project: Not ready for mainspace, incubate in draftspace. Reason/s: no sourcesTag: moveToDraft← Previous edit Latest revision as of 03:57, 12 July 2024 edit undoFrost (talk | contribs)Extended confirmed users, Page movers, New page reviewers, Pending changes reviewers, Rollbackers54,748 edits AFC draftTag: moveToDraft 
Line 1: Line 1:
{{AfC submission|t||ts=20240712035752|u=Shoila|ns=118|demo=}}
<h1>Sankhuwa Khola Hydropower Project</h1> <h1>Sankhuwa Khola Hydropower Project</h1>


Line 26: Line 27:
Promoters' Equity: 70% (NPR 1,395 7 million) Promoters' Equity: 70% (NPR 1,395 7 million)
Public Equity: 30% (NPR 598.1 million) Public Equity: 30% (NPR 598.1 million)
{{Drafts moved from mainspace |date=July 2024}}

Latest revision as of 03:57, 12 July 2024

Draft article not currently submitted for review.

This is a draft Articles for creation (AfC) submission. It is not currently pending review. While there are no deadlines, abandoned drafts may be deleted after six months. To edit the draft click on the "Edit" tab at the top of the window.


To be accepted, a draft should:

It is strongly discouraged to write about yourself, your business or employer. If you do so, you must declare it.


Where to get help
  • If you need help editing or submitting your draft, please ask us a question at the AfC Help Desk or get live help from experienced editors. These venues are only for help with editing and the submission process, not to get reviews.
  • If you need feedback on your draft, or if the review is taking a lot of time, you can try asking for help on the talk page of a relevant WikiProject. Some WikiProjects are more active than others so a speedy reply is not guaranteed.
How to improve a draft

You can also browse Misplaced Pages:Featured articles and Misplaced Pages:Good articles to find examples of Misplaced Pages's best writing on topics similar to your proposed article.

Improving your odds of a speedy review

To improve your odds of a faster review, tag your draft with relevant WikiProject tags using the button below. This will let reviewers know a new draft has been submitted in their area of interest. For instance, if you wrote about a female astronomer, you would want to add the Biography, Astronomy, and Women scientists tags.

Add tags to your draft Editor resources
Last edited by Frost (talk | contribs) 5 months ago. (Update) Submit the draft for review!

Sankhuwa Khola Hydropower Project

The Sankhuwa Khola Hydropower Project is a 41.06 MW run-of-river hydroelectric project under construction in the Sankhuwasabha and Bhopur districts of Nepal. It is being developed by Guras Hydro Pvt. Ltd., a private limited company established in 2020.

Project Details

  • Location: Silichong Rural Municipality (Ward No- I), Sankhuwasabha District and Salpachilichho Rural Municipality (Ward No- 1), Bhojpur District
  • River Sankhuwa Khola, a tributary of the Arun River
  • Catchment Area: 334.808 sq- km
  • Design Discharge: 15250 cubic meters per second
  • Gross Head: 315.92 meters
  • Installed Capacity: 4106 MW
  • Annual Energy Generation: 244.745 GWh
  • Dry Season Energy: 79B44 GWh (32.42%)
  • Wet Season Energy: 165 a (679%)
  • Headworks: 42-meter-long boulder-filled concrete weir, intake, gravel trap, and settling basins
  • Waterway: 5,710-meter headrace tunnel, surge shaft, 725-meter penstock
  • Powerhouse: Open-type powerhouse with Francis vertical turbine units
  • Tailrace: 73-meter-long box culvert discharging into the Arun River
  • Transmission Line: 4 km, 132 kV single circuit line to Sitalpati 220 kV substation

    Project Cost and Financing

    Total Project Cost: NPR 7975R9 million (approximately USD 627 million) Cost per kW: NPR 194935 (USD 1 ,528) Debt: 75% (NPR 508101 million) Equity: (NPR 1,993 07 million) Promoters' Equity: 70% (NPR 1,395 7 million) Public Equity: 30% (NPR 598.1 million)