Yebatan Hydropower Station 叶巴滩水电站 | |
---|---|
Country | China |
Location | at the junction of Baiyu and Konjo |
Coordinates | 30°45′0″N 98°57′36″E / 30.75000°N 98.96000°E / 30.75000; 98.96000 |
Purpose | Power, flood control, navigation |
Construction began | March 2017 |
Opening date | June 27, 2017 |
Construction cost | ¥33.36 billion |
The Yebatan Hydropower Station (Chinese: 叶巴滩水电站) is the hydropower project with the largest installed capacity in the upper reaches of the Jinsha River. It is located at the junction of Baiyu County in Sichuan Province and Konjo County in Tibet Autonomous Region.
Since it is an arch dam, it is also called as the Yebatan Arch Dam, with a maximum height of 217 meters. The total investment in this project is ¥ 33.36 billion, and its first generating unit is expected to be operational by 2025, and the total installed capacity is 2.24 million kilowatts.
History
In November 2016, the National Development and Reform Commission approved the construction of the Lawa Hydropower Station. On June 27, 2017, construction of the Yebatan Hydropower Station officially began.
On March 30, 2019, the upstream cofferdam of the plant was intercepted and the main construction of the project was fully underway.
References
- "Work begins on 2.24 GW hydropower plant". Shanghai Daily. 2019-04-01.
- "叶巴滩水电站大坝混凝土浇筑施工仿真研究 (Simulation Study on Dam Concrete Placement Construction at Yebatan Hydropower Station)". CNKI. 2019-01-01.
- ^ "Inventory of hydropower stations in Tibet". International Campaign for Tibet. May 30, 2019.
- "Construction of 2.24-GW hydropower station underway in upper Yangtze". Xinhuanet.com. 2019-03-31. Archived from the original on March 31, 2019.
- Zhang, Wen; Chen, Yuan; Yang, Bao-Quan; Zhang, Lin; Zhang, Chong; Liu, Xiao-Qiang (4 February 2019). "Experimental and numerical analyses on working performance of a high arch dam with deep-seated joints: Yebatan arch dam, China". Arabian Journal of Geosciences. 12 (4): 103. Bibcode:2019ArJG...12..103Z. doi:10.1007/s12517-019-4256-9. S2CID 134523731.
- "Reuters Basis Point:Yebatan Hydropower Station received RMB 26.7 billion in 32-year loans". Reuters. Jun 5, 2017.
- "China begins building major new power station in Tibet". Tibetan Review. April 2, 2019.
- "Changdu builds a national "West-to-East Power Transmission" connection base and accelerates". People's Daily. Mar 17, 2020.
- "The upstream of the Jinsha River has witnessed a period of rapid construction for hydropower development". Xinhuanet.com. 2019-04-03.
- "Largest upstream hydropower station on the Jinsha River intercepts flows". Xinhuanet.com. 2019-03-30. Archived from the original on March 31, 2019.
Energy in China | |
---|---|
Topics | |
Agencies | |
Sources | |
Electricity generation and transmission | |
State-owned energy companies | |
This article about a hydroelectric power plant is a stub. You can help Misplaced Pages by expanding it. |