Article snapshot taken from Wikipedia with creative commons attribution-sharealike license.
Give it a read and then ask your questions in the chat.
We can research this topic together.
An amount of Rs 227 crore contract to build this station along with a mostly at-grade 2.16 km (1.34 mi) section from the Bagjola Canal to the existing ramp of the Airport Circular Railway track was awarded to Senbo Engineering Limited all the way back in June 2011. Since then, the station’s civil structure has been built, but work for the at-grade track section could not be started due to land acquisition issues along the line’s proposed alignment. But the rehabilitation work has completed in 2020, and the work is going smoothly. Recently girders were placed over Eastern Railway tracks. The metro station is set to be operational by 2025.
Project development
Project development
The project will be completed in three phases. The first phase of work from Noapara to Biman Bandar is under progress. In the second phase work from Biman Bandar to New Barrackpore will be done and in the last phase from New Barrackpore to Barasat work will be done. But the development work from New Barrackpore to Barasat got struck for the last eight years since it was sanctioned because of encroachments. and the Airport Authority of India objected the elevated stretches from New Barrackpore to Barasat. Later, after objections from AAI, a decision was taken to convert this into an underground stretch. On 29 June 2019 sanction for material modification for underground construction at an additional cost of ₹1,615 crore (US$190 million) was sent to Railway Board by Metro. For this underground tunneling AAI has agreed to shift their fuel tanks, buildings and cables and the project is expected to be started from 2020.
Construction of an underground integrated station for Line 6 and Line 4 has begun at NSCBI Airport land just 150 metres (492 ft) away from the terminal building.
The development of New Barrackpore to Barasat was supposed to go elevated to cut down the expenses, but the stretch was in doubt due to huge encroachment problem. But in February 2021, Prime Minister Narendra Modi gave his nod to construct this stretch underground, giving respite to thousands of families who were supposed to be evicted for the development of the elevated stretch. In order to lower the cost of the underground work, latest technology TBM will not be used, instead old technology of cut and cover method will be used for metro.
Line 4 has been divided into three phases.
Phase 1: Noapara - Biman Bandar (Under trials)
Phase 2: Biman Bandar - New Barrackpore (under construction till Michael Nagar; Michael Nagar - New Barrackpur section is waiting for AAI approval)
Phase 3: New Barrackpore - Barasat (stuck due to land acquisition)